75 FERC 61,080

UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION

Promoting Wholesale Competition Through Open Access Services by Public Utilities

Recovery of Stranded Costs by Public Utilities and Transmitting Utilities


Docket No. RM95-8-000

Docket No. RM94-7-001

ORDER NO. 888
FINAL RULE
(Issued April 24, 1996)


IV. DISCUSSION

F. Coordination Arrangements: Power Pools, Public Utility Holding Companies, Bilateral Coordination Arrangements, and Independent System Operators


Comments

Timing of Reformation

Many marketers, IPPs, and other nonmembers of pools request that the Commission immediately apply unbundling and transmission tariff requirements to all new transactions under existing pooling agreements. APPA states that the Commission should not deal with power pools as a "follow-on activity" because treatment of pools is an integral step in achieving transmission comparability. AEC contends that until pools publish open access tariffs, the Commission should permit applications for section 211 transmission orders from one or more applicants directed to multiple respondents.

Existing pools generally urge the Commission to allow time for the pools to propose alternative structures or agreements which would meet the objectives of the final rule. EEI states that the rule may create problems for power pools that will not be examined or understood by the Commission and the public until the Commission's pooling inquiry is completed; it requests that the pooling inquiry be completed before a final rule is issued. Duke recommends that implementation of open access transmission services by power pools be addressed in a separate proceeding because implementation of open access for power pools raises complex issues.

EGA, among others, argues that new transactions under existing pooling agreements should not be grandfathered, but rather should be required to meet the functional unbundling requirements of the final rule. Some pool members argue that pool transactions are largely not wholesale transactions. For example, PECO (a member of PJM) requests the Commission to clarify that the delivery of pooled generation to pool members' native load is not a "wholesale purchase" of power and thus would not require taking transmission service under one's own open access transmission tariff. Another member of PJM, BG&E, interprets the proposed rule to require all PJM economy trades to be firm point-to-point services; it claims that such a requirement "jeopardizes the continued viability of the pool."

System-wide tariffs

Virtually all commenters on power pool issues state that the tariff requirements should not be applied directly to individual utilities who are members of "tight" power pools. ELCON, CCEM, and others argue that the pro forma tariff requirement should be applied directly to "tight" or "single system" power pools to avoid discriminatory "pancaking" of transmission rates. However, Duke argues that where there are both multiple owners and operators, as in "loose" pools, it is appropriate to have individual tariffs unless the pool members agree otherwise. DOE recommends a power pool file a single pool-wide tariff to offset problems associated with joint ownership or control of transmission. CT DPUC recommends that the Commission provide guidance for transmission access and pricing (so as to avoid needless disruption of present methods).

Flexible Treatment

Most commenters on power pools support recognizing regional differences among power pools and urge flexibility. PSE&G (a member of PJM) states that open access tariffs must be specially crafted to deal with power pool members. NYPP and PJM state that they are considering innovations and urge that their efforts not be stifled by any final rule. CSW proposes a region-wide pricing model based on power flows. NPPD, a member of the Mid-Continent Area Power Pool (MAPP), says MAPP is considering adopting the megawatt-mile approach to transmission pricing. SoCal Edison states that California utilities are developing a market-based power pool and that it is crucial for the final rule to be flexible to permit innovations throughout the country.

ELCON and power marketers, however, argue for uniformity and point out the difficulties of moving power from system to system where each system has varying standards or "pool rules." These commenters support uniform application of the terms and conditions in the pro forma tariffs to create a national standard.

NEPOOL emphasizes that since pools remain voluntary, the imposition of rules that are not acceptable to pool members simply increases the likelihood that members will withdraw and pools will disintegrate. For this reason, NEPOOL states that solutions to enhance competition (within a tight pool setting) are best identified through the consensus of pool members, which requires both time and flexibility on the part of the Commission.

DE, DC, NJ and MD Coms emphasizes its concern that a one- size-fits-all open-access policy, while perhaps benefiting subsets of individual suppliers and purchasers, may not be the best solution for the millions of retail customers who currently rely on power pools. 405/ It wants the Commission to be aware that the individual commissions have begun a formal dialog among each other and with the PJM utilities to discuss possible regional solutions to transitional competitive issues.

Open Membership

NIEP and CCEM argue that the competitive playing field cannot be level unless nonmembers receive certain power pool services on terms comparable to those for pool members. Members of pools state that "return in kind" transactions are efficient, but that such transactions are not appropriate for those entities that are not similarly situated to vertically integrated utilities.

EEI maintains that those seeking the benefits of pool membership must accept the burdens imposed on existing pool members (otherwise, they would have an advantage, not comparability). EEI believes that new pool participants can negotiate and "buy into" the pool resources. Many commenters claim that unbundling certain power pool services to accommodate open access will solve the problem.

MidAmerican states that if the Commission grants nonmembers access to pool transmission service, the Commission should allow a period of at least four years for pools to restructure and refile rate schedules to avoid the inequitable results which the Commission's requirements will impose on pool members.

MidAmerican contends that the Commission should authorize pool members to unilaterally withdraw from their pools if any restructuring or revision of rate schedules is unacceptable to the member.

Holding companies

Allegheny, Southern, and other holding companies argue that coordination agreements among subsidiaries of a utility holding company system do not constitute a power pool and should not be subject to any obligations the Commission may place on power pools.

Bilateral Coordination Agreements

Ohio Edison requests clarification that the Commission is not requiring new wholesale coordination transactions to be under the open access tariffs; they may be continued under existing coordination agreements. It stresses the importance of such agreements in making economy and emergency transactions.

A number of commenters agree that existing coordination contracts should not be abrogated or modified, and that transactions under these existing contracts should not be governed by the provisions of the pro forma tariffs. 406/ These commenters generally argue that existing coordination agreements should not be abrogated or amended by the final rule because: (1) they were not negotiated in the environment envisioned by the NOPR; (2) coordination sales are beneficial to consumers and ratepayers (and thus it would not be in the public interest to curtail them); and (3) the termination of coordination agreements, which in some cases have been in place for years and are tailored to parties' peculiar circumstances, could cause severe hardships in certain regions (especially with regard to scheduling and curtailment).

PSNM contends that such agreements are the result of mutually beneficial bargaining. LPPC and MEAG argue that current contracts negotiated among parties provide cost savings to consumers, which may be foregone if existing contracts are modified. Central Louisiana suggests that the pro forma tariff provisions should be flexible enough to achieve comparability if applied to both existing and new coordination agreements.

Some commenters argue that there may be cases where it is inappropriate to modify existing coordination agreements to satisfy the requirements of the rule. They assert that coordination agreements providing for emergency transactions, 407/ reliability, 408/ and resource efficiency gains 409/ need special attention. However, Soyland believes that existing agreements need to be reviewed if there is substantial increase in wholesale power market transactions, at the customer's option. TDU Systems argues that coordination contracts supporting system reliability should be honored and given scheduling and curtailment preference. TDU Systems contends that any amendments should be at the parties' discretion rather than by Commission mandate.

Several commenters suggest that the proposed rule is unclear about whether only existing transactions under agreements already approved by the Commission will be exempt from functional unbundling, or whether the proposed rule also would exempt (or grandfather) new transactions entered into pursuant to existing approved contracts. 410/ Other commenters recommend that the Commission clarify that its policy on unbundling applies to all new transactions, whether pursuant to new or existing agreements. 411/ ConEd and KCPL request clarification that purchases made to satisfy retail service are not subject to the requirements of the pro forma tariffs.

CCEM argues that all coordination transactions, including new transactions under existing agreements, should be unbundled to ensure that transmission providers are implementing the posted transmission rate. CINergy contends that the comparability standard should be applied to existing coordination agreements, including buy-resell agreements, to mitigate any unfair bulk power market advantages. Functional unbundling would ensure that a utility includes an EBB-posted transmission rate in the transaction charge. CINergy and Power Marketing Association recommend that the Commission use its authority under section 206 to require all utilities to file amendments to their existing coordination agreements providing for transmission service to be taken pursuant to the parties' open access transmission tariffs. Power Marketing Association further recommends that the Commission establish expedited procedures to address the situation arising from conflicting pro forma tariffs and existing coordination provisions.

Tallahassee also believes that the comparability standard should be applied to existing coordination agreements, but Tallahassee recommends that the Commission establish a transition period to allow for renegotiation among parties rather than imposing modifications to existing agreements. Renegotiation would provide an opportunity to retain previously bargained-for benefits. Detroit Edison also contends that many of the existing coordination agreements do not provide for the services required under the pro forma tariffs. Like Tallahassee, Detroit Edison recommends that the Commission allow sufficient time for parties to renegotiate existing agreements. CINergy suggests a three- year transition period.

Coordination Pricing Practices

EEI and PJM disagree with the Commission's assertion that current coordination pricing is no longer just and reasonable in the absence of an open access tariff. Ohio Edison and PA Com question the basis of the Commission's preliminary conclusion that current coordination pricing is no longer justified in the absence of a seller's tariff offer of non-discriminatory open access transmission services. PA Com asserts that the Commission's underlying assumption of general lack of transmission access by wholesale customers has not been established as fact in the proposed rule.

MN DPS supports current coordination pricing methods provided that utilities have executed open-access tariffs. Missouri Basin Group argues that, if increased market competition materializes through open access, utilities will decreasingly rely on current coordination pricing if it no longer produces the most beneficial outcome. Missouri Basin Group recommends the Commission simply allow utilities to choose a pricing method even if a utility opts for a less beneficial outcome. Nebraska Public Power District also urges the Commission to avoid mandating coordination pricing methods. Nebraska Public Power District is concerned that this may impede establishing RTGs where such pricing is by mutual agreement and subject to ADR procedures.

Several commenters agree that current coordination pricing may no longer be appropriate in an open access regime. 412/ FL Com believes that current coordination pricing should be replaced by market-based rates if open access transmission service is imposed by the Commission.

Commission Conclusion

The term "coordination" is applied to a wide variety of wholesale power sales agreements within the industry, including interchange, interconnection, pooling, and other agreements. Broadly speaking, any non-requirements power sales agreement can be considered to be a coordination agreement. 413/

The Final Rule's general requirement for non-discriminatory transmission access and pricing by public utilities, and its specific requirement that public utilities unbundle their transmission rates and take transmission service under their own tariffs, apply to all public utilities' wholesale sales and purchases of electric energy, including coordination transactions. The Commission has determined that certain existing wholesale coordination arrangements and agreements must be modified to ensure that necessary transmission services for such arrangements and agreements are taken under open access transmission tariffs and thus that such arrangements and agreements are not unduly discriminatory. Below we discuss how and when various types of coordination agreements will need to be modified, and when public utility parties to coordination agreements must begin to trade power under those agreements using transmission service obtained under the same open access transmission tariff available to non-parties.

Coordination arrangements, and the agreements governing them, vary widely. They range from relatively simple bilateral arrangements to complex tight power pools. Our discussion addresses four broad categories of arrangements and accompanying agreements: "tight" power pools, "loose" power pools, public utility holding company arrangements, and bilateral coordination arrangements. For purposes of implementing the non- discriminatory, open access requirements of the Final Rule, we are dividing bilateral coordination agreements into two general categories: bilateral economy energy agreements and other bilateral coordination agreements. Economy energy agreements typically provide for short-term economy trading "if, as, and when available" and are generally driven by the buyer and seller's generation costs. They do not require either the seller or the buyer to engage in a particular transaction. Other coordination agreements are typically longer term or open-ended. Some may involve joint ownership or joint planning of generation. 414/ Others may provide joint operation of facilities so that the parties can coordinate their maintenance schedules or provide one another with emergency service. These longer-term coordination agreements are distinguished from short-term economy trading agreements in that the parties have undertaken a contractual obligation to operate their facilities so as to support one another under the conditions specified in the arrangements.

As noted in the NOPR, power pools, in contrast to most bilateral arrangements, present complex issues that may require special implementation requirements. 415/ This is because these arrangements may involve agreements containing an intricate set of rights, obligations, and considerations among the members of a pool. We provide for implementation requirements herein that vary depending upon the type of "pooling" arrangement involved.

The Commission has concluded that in order to adequately remedy the undue discrimination in transmission access and pricing by public utilities that are members of power pools or other coordination arrangements, such public utilities must remove preferential transmission access and pricing provisions from agreements governing their transactions. The filing of open access tariffs by the public utility members of a power pool is not enough to cure undue discrimination in transmission if those public utilities can continue to trade with a selective group within a power pool that discriminatorily excludes others from becoming a member and that provides preferential intra-pool transmission rights and rates. The same holds true of certain bilateral arrangements that allow preferential transmission pricing or access. These arrangements and agreements need to be changed. We expect such arrangements and agreements to be modified by the dates indicated in this Rule. However, if necessary, we will institute section 206 proceedings against public utilities that do not make such filings.

The Commission's technical conferences on power pools, ISOs, and pro forma tariffs made clear to us the need to articulate guidance in this Rule on the restructuring or modification of unduly discriminatory coordination arrangements -- particularly tight power pools. 416/ They also made clear that members of tight power pools, in particular, need time to make the necessary modifications to these arrangements. We recognize that members of some power pools are already in the process of formulating voluntary modifications to pooling agreements to be filed with the Commission (e.g., PJM, NYPP, NEPOOL). Therefore, we will provide adequate time for these filings as well as guidance to changes that need to be made.

In addition, although we do not at this time find it necessary to require power pools to form an independent system operator in order to remedy undue discrimination, we believe ISOs may prove to be an effective means for accomplishing comparable access. 417/ We recognize that several utilities are exploring the possibility of forming ISOs. For example, discussions are ongoing in California, PJM, NYPP, and the Midwest. Therefore, because of the industry's interest (which we share) in the concept of an ISO and the potential for an ISO to provide non-discriminatory transmission services to all market participants, we will provide guidance in this section on minimum ISO characteristics.

1. Tight Power Pools

For purposes of this Rule, the tight power pools are: New York Power Pool (NYPP), New England Power Pool (NEPOOL), Pennsylvania-New Jersey-Maryland Interconnection (PJM), and the Michigan Electric Coordinated Systems (MECS).

Public utilities who are members of a tight pool must file, within 60 days of publication of the Final Rule in the Federal Register, either: (1) an individual Final Rule pro forma tariff; or (2) a joint pool-wide Final Rule pro forma tariff. They are not required to take service for pool transactions under the tariff that is filed within 60 days. However, they will be required to file a joint pool-wide Final Rule pro forma tariff no later than December 31, 1996, and must begin to take service under that tariff for all pool transactions no later than December 31, 1996. The purpose of this extension is to allow sufficient time for tight pools to amend their pooling agreements and to restructure their operations to conform to the requirements of the Final Rule. We also believe that the additional time is necessary to preserve efficient trading arrangements during the restructuring period.

The Commission therefore will require that the public utility members of tight pools file reformed power pooling agreements no later than December 31, 1996. The reformed power pool agreements should establish open, non-discriminatory membership provisions (including establishment of an ISO, if that is a pool's preferred method of remedying undue discrimination) and modify any provisions that are unduly discriminatory or preferential. The membership provision must allow any bulk power market participant to join, regardless of the type of entity, affiliation, or geographic location.

If the reformed agreement allows members to make transmission commitments or contributions in exchange for the discounted transmission rates, the pool may file a transmission tariff that contains an access fee for non-transmission owning members or non-members, justified solely on the basis of transmission-related costs. Alternatively, the pool could make available a transmission rate that is structured the same as the discounted rate (e.g., non-pancaked) but with a higher rate that is justified on the basis of transmission-related costs borne (or contributed) by the pool members. However, any such access fee or higher rate must be justified solely on the basis of transmission costs and cannot be tied to the costs of any other agreement among the pool members (e.g., generation reserve sharing).

2. Loose Pools

For purposes of the Final Rule, a loose pool is any multi- lateral (more than 2 public utilities) arrangement, many of which contain discounted and/or special transmission arrangements. Examples are MAPP, Inland Power Pool, and the MOKAN pool. Other entities may qualify to be treated as a loose pool if they can show that they meet the definition above.

Public utilities within a loose pool must file, within 60 days of publication of the Final Rule in the Federal Register, either: (1) an individual Final Rule pro forma tariff; or (2) a pool-wide Final Rule pro forma tariff. They are not required to take service for pool transactions under the tariff that is filed within 60 days. However, they will be required to file a joint pool-wide Final Rule pro forma tariff no later than December 31, 1996, and must begin to take service under that tariff for all pool transactions no later than December 31, 1996. The purpose of this extension is to allow sufficient time for loose pools to amend their agreements and to restructure their operations to conform to the requirements of the Final Rule. We also believe that the additional time is necessary to preserve efficient trading arrangements during the restructuring period.

The Commission therefore will require that the public utility members of loose pools file reformed power pooling agreements no later than December 31, 1996. They also must file a joint pool-wide tariff no later than December 31, 1996. The reformed power pool agreements should establish open, non- discriminatory membership provisions and modify any provisions that are unduly discriminatory or preferential. The membership provision must allow any bulk power market participant to join, regardless of the type of entity, affiliation, or geographic location.

The Commission recognizes that loose pools typically do not operate as a single control area and that operational unbundling, perhaps through an ISO, might not be readily attainable at this time. Nonetheless, we encourage the members of loose pools to explore the advantages of the ISO concept.

If the reformed agreement allows members to make transmission commitments or contributions in exchange for discounted transmission rates, the pool may file a transmission tariff that contains an access fee for non-transmission owning members or non-members, justified solely on the basis of transmission-related costs. Alternatively, the pool could make available a transmission rate that is structured the same as the discounted rate (e.g., non-pancaked) but with a higher rate that is justified on the basis of transmission-related costs borne (or contributed) by the pool members. However, any such access fee or higher rate must be justified solely on the basis of transmission costs and cannot be tied to the costs of any other agreement among the pool members (e.g., generation reserve sharing).

3. Public Utility Holding Companies

Public utility members of registered and exempt holding companies that are also members of tight or loose pools are subject to the tight and loose pool requirements set forth above. The remaining holding company public utility members, with the exception of the Central and South West (CSW) System, are required to file a single system-wide Final Rule pro forma tariff permitting transmission service across the entire holding company system at a single price within 60 days of publication of the Final Rule in the Federal Register (service companies may, of course, file on behalf of their public utility affiliates). As discussed below, CSW presents special circumstances.

The CSW System is comprised of four operating public utilities. Two of those utilities, Southwestern Electric Power Company (SWEPCO) and Public Service Company of Oklahoma (PSO) operate in the Southwest Power Pool (SPP). The other two, West Texas Utilities Company (West Texas) and Central Power and Light Company (CP&L), operate in the Electric Reliability Council of Texas (ERCOT). SWEPCO and PSO exchange power with West Texas and CP&L through two high voltage, direct current interconnections (the North and East Interconnections). 418/

Pursuant to the Commission orders concerning the North and East Interconnections, CP&L, West Texas, SWEPCO, and PSO have on file what are referred to as the "to or from and over tariffs." 419/ Those tariffs apply only to transmission service that involves the delivery of power and energy to or from and over the North and East Interconnections. 420/ The tariffs do not apply to the transmission of power for CSW subsidiaries other than the operating companies. The tariffs in many respects are different from the Final Rule pro forma tariff and do not provide comparable services. Moreover, the pricing provided in the "to or from and over" tariffs is different from the pricing set forth in the Texas Commission's final open access rule. 421/

Given these special circumstances, we believe it appropriate to give CSW the opportunity to propose a solution to achieving comparability for the CSW system. Accordingly, we direct the public utility subsidiaries of CSW to consult with the Texas, Arkansas, Oklahoma and Louisiana Commissions and to file not later than December 31, 1996 a system tariff that will provide comparable service to all wholesale users on the CSW System, 422/ regardless of whether they take transmission service wholly within ERCOT or the SPP, or take transmission service between the reliability councils over the North and East Interconnections. 423/

The Commission will give public utilities that are members of holding companies an extension of the requirement to take service under the system tariff for wholesale trades between and among the public utility operating companies within the holding company system. This extension is until December 31, 1996 -- the same extension we are granting to power pools. At that point, the public utility operating companies will be required to take service under the Final Rule pro forma tariff for wholesale trades among themselves. In addition, it may be necessary for registered holding companies to reform their holding company equalization agreement to recognize the non-discriminatory terms and conditions of transmission service required under the Final Rule pro forma tariff..

4. Bilateral Coordination Arrangements

Any bilateral wholesale coordination agreement executed after the effective date of this Rule will be subject to the functional unbundling and open access requirements set forth in this Rule. With regard to existing bilateral agreements, however, the diversity of the types of agreements currently on file presents special implementation problems. The Commission is particularly concerned with future economy energy transactions that may occur pursuant to existing umbrella-type coordination agreements. Accordingly, we shall require all bilateral economy energy coordination contracts executed before the effective date of this Rule to be modified to require unbundling of any economy energy transaction occurring after December 31, 1996. All non- economy energy bilateral coordination contracts executed before the effective date of this Rule will be permitted to continue in effect, but will be subject to complaints filed under section 206 of the FPA. Under those procedures, the rates, terms, and conditions of individual coordination contracts may be challenged as unduly discriminatory or otherwise unlawful.

To compute the unbundled coordination compliance rate, the utility must subtract the corresponding transmission unit charge in its open access tariff from the existing coordination rate ceiling. For example, if a utility has a coordination rate ceiling for hourly service of incremental cost plus 15 mills/kWh and a transmission tariff rate for hourly service of 3 mills/kWh, it shall revise the coordination rate ceiling to incremental cost plus 12 mills/kWh. The Commission cautions that the compliance filing will be strictly limited to removing the current transmission tariff price from the coordination price and will not be a medium for otherwise revising the residual coordination sales price.

The transmission rate for the coordination transactions may be at or below the tariff rate. However, if a utility's transmission operator offers a discounted transmission rate to the utility's wholesale marketing department or an affiliate for the purposes of coordination transactions, the same discounted rate must be offered to others for trades with any party to the coordination agreement. In addition, discounts offered to non- affiliates must be on a basis that is not unduly discriminatory. 424/ This may require parties to file modifications of the coordination arrangements.

ISO Principles

The Commission recognizes that some utilities are exploring the concept of an Independent System Operator and that the tight power pools are considering restructuring proposals that involve an ISO. While the Commission is not requiring any utility to form an ISO at this time, we wish to encourage the formation of properly-structured ISOs. To this end, we believe it is important to give the industry some guidance on ISOs at this time. Accordingly, we here set out certain principles that will be used in assessing ISO proposals that may be submitted to the Commission in the future.

These principles are applicable only to ISOs that would be control area operators, including any ISO established in the restructuring of power pools. We recognize that some utilities are exploring concepts that do not involve full operational control of the grid. Without in any way prejudging the merits of such arrangements, the following principles do not apply to independent administrators or coordinators that lack operational control. We do not have enough information at this time to offer guidance about such entities, but recognize that they could perform a useful role in a restructured industry.

Because an ISO will be a public utility subject to our jurisdiction, 425/ the ISO's operating standards and procedures must be approved by the Commission. In addition, a properly constituted ISO is a means by which public utilities can comply with the Commission's non-discriminatory transmission tariff requirements. The principles for ISOs are:

  1. The ISO's governance should be structured in a fair and non-discriminatory manner.

    The primary purpose of an ISO is to ensure fair and non-discriminatory access to transmission services and ancillary services for all users of the system. As such, an ISO should be independent of any individual market participant or any one class of participants (e.g., transmission owners or end-users). A governance structure that includes fair representation of all types of users of the system would help ensure that the ISO formulates policies, operates the system, and resolves disputes in a fair and non-discriminatory manner. The ISO's rules of governance, however, should prevent control, and appearance of control, of decision-making by any class of participants.
  2. An ISO and its employees should have no financial interest in the economic performance of any power market participant.

    An ISO should adopt and enforce strict conflict of interest standards. To be truly independent, an ISO cannot be owned by any market participant. We recognize that transmission owners need to be able to hold the ISO accountable in its fiduciary role, but should not be able to dictate day-to-day operational matters. Employees of the ISO should also be financially independent of market participants. We recognize, however, that a short transition period (we believe 6 months would be adequate) will be needed for employees of a newly formed ISO to sever all ties with former transmission owners and to make appropriate arrangements for pension plans, health programs and so on. In addition, an ISO should not undertake any contractual arrangement with generation or transmission owners or transmission users that is not at arm's length. In order to ensure independence, a strict conflict of interest standard should be adopted and enforced.
  3. An ISO should provide open access to the transmission system and all services under its control at non-pancaked rates pursuant to a single, unbundled, grid-wide tariff that applies to all eligible users in a non-discriminatory manner.

    An ISO should be responsible for ensuring that all users have non-discriminatory access to the transmission system and all services under ISO control. The portion of the transmission grid operated by a single ISO should be as large as possible, consistent with the agreement of market participants, and the ISO should schedule all transmission on the portion of the grid it controls. An ISO should have clear tariffs for services that neither favor nor disfavor any user or class of users.
  4. An ISO should have the primary responsibility in ensuring short-term reliability of grid operations.

    Its role in this responsibility should be well-defined and comply with applicable standards set by NERC and the regional reliability council. Reliability and security of the transmission system are critical functions for a system operator. As part of this responsibility an ISO should oversee all maintenance of the transmission facilities under its control, including any day-to-day maintenance contracted to be performed by others. An ISO may also have a role with respect to reliability planning. In any case, the ISO should be responsible for ensuring that services (for all users, including new users) can be provided reliably, and for developing and implementing policies related to curtailment to ensure the on-going reliability and security of the system.
  5. An ISO should have control over the operation of interconnected transmission facilities within its region.

    An ISO is an operator of a designated set of transmission facilities.
  6. An ISO should identify constraints on the system and be able to take operational actions to relieve those constraints within the trading rules established by the governing body.

    These rules should promote efficient trading. A key function of an ISO will be to accommodate transactions made in a free and competitive market while remaining at arm's length from those transactions. The ISO may need to exercise some level of operational control over generation facilities in order to regulate and balance the power system, especially when transmission constraints limit trading over interfaces in some circumstances. It is important that the ISO's operational control be exercised in accordance with the trading rules established by the governing body. The trading rules should promote efficiency in the marketplace. In addition, we would expect that an ISO would provide, or cause to be provided, the ancillary services described in this Rule.
  7. The ISO should have appropriate incentives for efficient management and administration and should procure the services needed for such management and administration in an open competitive market.

    Management and administration of the ISO should be carried out in an efficient manner. In addition to personnel and administrative functions, an ISO could perform certain operational functions, such as: determination of appropriate system expansions, transmission maintenance, administering transmission contracts, operation of a settlements system, and operation of an energy auction. The ISO should use competitive procurement, to the extent possible, for all services provided by the ISO that are needed to operate the system. All procedures and protocols should be publicly available.
  8. An ISO's transmission and ancillary services pricing policies should promote the efficient use of and investment in generation, transmission, and consumption.

    An ISO or an RTG of which the ISO is a member should conduct such studies as may be necessary to identify operational problems or appropriate expansions. Appropriate price signals are essential to achieve efficient investment in generation and transmission and consumption of energy. The pricing policies pursued by the ISO should reflect a number of attributes, including affording non-discriminatory access to services, ensuring cost recovery for transmission owners and those providing ancillary services, ensuring reliability and stability of the system and providing efficient price signals of the costs of using the transmission grid. In particular, the Commission would consider transmission pricing proposals for addressing network congestion that are consistent with our Transmission Pricing Policy Statement. In addition, an ISO should conduct such studies and coordinate with market participants including RTGs, as may be necessary to identify transmission constraints on its system, loop flow impacts between its system and neighboring systems, and other factors that might affect system operation or expansion.
  9. An ISO should make transmission system information publicly available on a timely basis via an electronic information network consistent with the Commission's requirements.

    A free-flow of information between the ISO and market participants is required for an ISO to perform its functions and for market participants to efficiently participate in the market. At a minimum, information on system operation, conditions, available capacity and constraints, and all contracts or other service arrangements of the ISO should be made publicly available. This information should be made available on an OASIS operated by the ISO.
  10. An ISO should develop mechanisms to coordinate with neighboring control areas.

    An ISO will be required to coordinate power scheduling with other entities operating transmission systems. Such coordination is necessary to ensure provision of transmission services that cross system boundaries and to ensure reliability and stability of the systems. The mechanisms by which ISOs and other transmission operators coordinate can be left to those parties to determine.
  11. An ISO should establish an ADR process to resolve disputes in the first instance.

    An ISO should provide for a voluntary dispute resolution process that allows parties to resolve technical, financial, and other issues without resort to filing complaints at the Commission. We would encourage the ISO to establish rules and procedures to implement alternative dispute resolution processes.



Convergence Research - 5/2/96